About the project

In the Grafental Ost quarter of Düsseldorf-Flingern-Nord, nyoo, a subsidiary of the Instone group, started building 167 homes in July 2026. The company places the scheme in its affordable-housing segment. The buildings follow the EH 40 energy standard. The publicly available report does not say whether the apartments will be rented or sold, how many are subsidised, or when they are due to be finished. The project lies in the same urban quarter as Instone's Mosaik scheme and adds to the development in the eastern part of Grafental. Further details are likely to be published once marketing begins.

New-build projects

Project facts

Each line names its source and the date on which we checked the fact there. If a line is missing, no source has published that fact.

Project facts

Item
Developer
Value
Nyoo Real Estate GmbH (Instone-Gruppe)
Source
koniichecked 10 November 2026
Item
Location
Value
Düsseldorf-Flingern-Nord
Source
koniichecked 10 November 2026
Item
Apartments
Value
167
Source
koniichecked 10 November 2026
Item
Project stage
Value
under construction · Construction start reported 15.07.2026
Source
koniichecked 10 November 2026
Item
Energy standard
Value
EH 40 standard
Source
koniichecked 10 November 2026

No individual listings: we do not show individual apartments, floor plans, photos or prices per apartment. Only the provider can confirm whether apartments are still available, what they cost and when they will be completed.

MaBV · § 556f BGB · WBS

Context

New-build projects

More new-build projects in Düsseldorf-Flingern-Nord

More new-build projects in Düsseldorf-Flingern-Nord

Location
Flingern-Nord
Developer
Instone Real Estate Development GmbH
Units
215
Type
for sale and for rent
Stage
under construction
Completion
Q3 2028
Location
Eller
Developer
Vivawest GmbH
Units
259
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
Mid-2028, first occupancy fall 2028
Location
Golzheim
Developer
SWD Städtische Wohnungsgesellschaft Düsseldorf
Units
215
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
2028
Location
Unterbilk
Developer
SWD Städtische Wohnungsgesellschaft Düsseldorf
Units
190
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
Summer 2028
Location
Lierenfeld
Developer
SWD Städtische Wohnungsgesellschaft Düsseldorf
Units
154
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
First 33 apartments and daycare center from December 2026, all apartments by H1 2027
Location
Unterbilk
Developer
BPD Immobilienentwicklung GmbH
Units
149
Type
rental apartments
Stage
under construction
Completion
End of 2028, first occupancy early 2029