DDORF WOHNEN
New-build project · Düsseldorf

Chemnitzer Straße 1–1b (SWD) – new build in Düsseldorf-Vennhausen

As of: 11 November 2026

completed · rental apartments / subsidized housing (geförderter Wohnungsbau) · 44 apartments

Illustration (AI generated): St. Katharina in Vennhausen · stylized according to photo reference
Location: Düsseldorf-Vennhausen
Open Data Düsseldorf · dl-de/zero-2.0
Own compilation

About the project

The municipal housing company SWD has built a rental building with 44 barrier-free apartments at Chemnitzer Straße 1–1b in Düsseldorf-Vennhausen. It consists of three connected sections of three to eight storeys with two small towers. 24 apartments are publicly subsidised and were allocated through the city housing office; 20 are privately financed. Units range from one to four rooms. According to SWD, the building is designed as an Effizienzhaus 55 and is heated with heat pumps, while rooftop photovoltaics supply tenant electricity. The first tenants moved in in February 2026, so the project is complete. A playground, an underground car park and bicycle storage are part of the site.

Project page of the developer (SWD Städtische Wohnungsgesellschaft Düsseldorf)

New-build projects

Project facts

Each line names its source and the date on which we checked the fact there. If a line is missing, no source has published that fact.

Project facts

Item
Developer
Value
SWD Städtische Wohnungsgesellschaft Düsseldorf
Item
Location
Value
Düsseldorf-Vennhausen, Chemnitzer Straße 1–1b
Item
Type
Value
rental apartments / subsidized housing (geförderter Wohnungsbau)
Item
Apartments
Value
44 (44 barrier-free rental apartments in three building sections; 24 publicly subsidised (18 funding path A, 6 path B), 20 privately financed; about 2,800 m² of living space in total)
Item
Subsidized apartments
Value
24
Item
Apartment types
Value
1–4 rooms (15× 1-room, 11× 2-room, 9× 3-room, 9× 4-room)
Item
Project stage
Value
completed · Completed; first tenants moved in in February 2026
Item
Completion according to source
Value
Completed, first occupancy from February 2026
Item
Energy standard
Value
Effizienzhaus 55, air-to-water heat pumps (supplemented by a gas condensing boiler), photovoltaics with tenant electricity on the two tower roofs, partly green roofs

No individual listings: we do not show individual apartments, floor plans, photos or prices per apartment. Only the provider can confirm whether apartments are still available, what they cost and when they will be completed.

MaBV · § 556f BGB · WBS

Context

The rent cap (Mietpreisbremse) does not apply to new apartments first let after 1 October 2014 (§ 556f BGB). If a graduated or index-linked rent is offered, calculate it over several years before signing.

For the subsidized apartments you need a housing entitlement certificate (WBS). They are allocated directly by the housing company; register there as a home seeker.

New-build projects

More new-build projects in Düsseldorf

More new-build projects in Düsseldorf

Location
Eller
Developer
Vivawest GmbH
Units
259
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
Mid-2028, first occupancy fall 2028
Location
Flingern-Nord
Developer
Instone Real Estate Development GmbH
Units
215
Type
for sale and for rent
Stage
under construction
Completion
Q3 2028
Location
Golzheim
Developer
SWD Städtische Wohnungsgesellschaft Düsseldorf
Units
215
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
2028
Location
Unterbilk
Developer
SWD Städtische Wohnungsgesellschaft Düsseldorf
Units
190
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
Summer 2028
Location
Flingern-Nord
Developer
Nyoo Real Estate GmbH (Instone-Gruppe)
Units
167
Type
–
Stage
under construction
Completion
–
Location
Lierenfeld
Developer
SWD Städtische Wohnungsgesellschaft Düsseldorf
Units
154
Type
rental apartments / subsidized housing (geförderter Wohnungsbau)
Stage
under construction
Completion
First 33 apartments and daycare center from December 2026, all apartments by H1 2027

Is a fact wrong or out of date? Report content

Data sources

Official source · Our own calculation · Our own analysis · DDORF estimate → Methodology

As of · Source: developers, cities and press